TODA CORPORATION
Major recent achievements
- Niigata City General Hospital
-

Year completed: 2007
Client: City of Niigata
Location: Niigata City, Niigata
Construction: New construction S 10/0 50,959m2 (JV) total
- New Hospital, Tokai University Hospital
-

Year completed: 2005
Client: Tokai University
Designer: Toda Corp.
Location: Isehara City, Kanagawa
Construction: New construction RC 14/1 69,509m2 (JV) total
- Okuma Auditorium, Waseda University
-

Year completed: 2007
Client: Waseda University
Location: Shinjuku, Tokyo
Construction: Renovation SRC 3/1 21,545m2 total
- 100th Anniversary centenary Hall, Tokyo College of Music
-

Year completed: 2007
Client: Tokyo College of Music
Location: Toshima, Tokyo
Construction: New construction S 4/1 9,687m2 total
- R&D Building, Konica Minolta Opto, Inc.
-

Year completed: 2008
Client: Konica Minolta Engineering Co., Ltd.
Designer: Toda Corp.
Location: Sayama City, Osaka
Construction: New construction S 6/0 15,448m2 total
- Fujikatsuyama Plant, Makino Milling Machine Co., Ltd.
-

Year completed: 2008
Client: Makino Milling Machine Co., Ltd.
Location: Fujikawaguchikomachi, Yamanashi
Construction: New construction S 2/0 9,832m2 total
- Osaka Main Branch, Yamato Transport Co., Ltd.
-

Year completed: 2007
Client: Yamato Transport Co., Ltd.
Location: Osaka City, Osaka
Construction: Addition SRC 6/0 59,276m2 total
- Sendai Nakano Distribution Center
-

Year completed: 2007
Client: Sendai Nakano Distribution Center
Designer: Toda Corp.
Location: Sendai City, Miyagi
Construction: New construction S 2/0 21,644m2 total
- Head Office Building, Fukuoka Financial Group
-

Year completed: 2008
Client: Fukuoka Bank
Location: Fukuoka City, Fukuoka
Construction: New construction S 14/1 27,726m2 total
- Administrative Building, Tochigi Prefectural Government
-

Year completed: 2007
Client: Tochigi Prefecture
Location: Utsunomiya City, Tochigi Prefecture
Construction: New construction S 15/2 55,913m2 (JV) total
- Morinodai Maple Land
-

Year completed: 2008
Client: Yokohama City Housing Supply Corp.
Designer: Toda Corp.
Location: Yokohama City, Kanagawa
Construction: New construction RC 14/0 36,272m2 total
- KOKURA TOWER
-

Year completed: 2008
Client: The Chuo Mitsui Trust and Banking Co., Ltd.
Location: Kitakyushu City, Fukuoka
Construction: New construction RC 28/2 22,724m2 total
- Yokohama Grand InterContinental Hotel, Pacifico Yokohama
-

Year completed: 1991
Client: Pacifico Yokohama
Location: Yokohama City, Kanagawa
Construction: New construction S 31/1 108,230m2 (JV) total
- Yurakucho Itocia (Yurakucho Marui)
-

Year completed: 2007
Client: Yurakucho Ekimae District 1 Urban Deveropment Association/Marui
Location: Chiyoda, Tokyo
Construction: New construction SRC 21/4 75,874m2 (JV) total
- Sakamoto Tunnel No. 2
-

Year completed: 2007
Client: Shikoku Regional Development Bureau
Location: Shimanto City, Kochi
Construction: NATM method, tunnel extension 1,074 m, Tomoshige Tunnel 127 m, Sakamoto Tunnel No. 2 887 m (JV)
- Tokyo Bay Aqua-Line
-

Year completed: 1997
Client: Trans-Tokyo Bay Highway Corp.
Location: Kawasaki City, Kanagawa
Construction: Construction extension 2.1 km, shield outer diameter 14.1 m (JV)
- Kansai International Airport Phase 2 Island Reclamation
-

Year completed: 2003
Client: Kansai International Airport
Location: Izumisano City, Osaka
Construction: Landfill: direct fill 5.36 million m3, dredged 14.6 million m3, ground leveling 960,000 m2 (JV)
- Yamadagawa Dam
-

Year completed: 2005
Client: Hiroshima Prefecture
Location: Sera Town, Hiroshima
Construction: Concrete gravity dam, height 32.1 m, crest length 204.8 m, volume 43,970 m3
- Hanshin Expressway Shimoyamaguchi Section
-

Year completed: 2002
Client: Hanshin Expressway Public Corporation
Location: Nishinomiya City, Hyogo
Construction: Construction extension 911 m, 35 RC bridge piers, 3 abutments, retaining walls: 459.3 m, RC precast 52.5 m (JV)
- Nishi-Waseda Station
-

Year completed: 2008
Client: Tokyo Metro Co., Ltd.
Location: Shinjuku, Tokyo
Construction: Open-cut construction, total length 78.2 m, width 22-38 m, depth 31-34 m; station building: RC, total floor space 3,999 m2, 1 aboveground story, 3 below ground stories